The construction site of sludge treatment equipment should be prepared
2022-03-07 From: Shangqiu hengze environmental protection equipment Co., Ltd Browsing times:19
The construction site of sludge treatment equipment should be prepared
1. The civil engineering is completed, and the basic conditions for the installation are available.
2. The site has been leveled, and the construction, transportation and firefighting roads have been cleared.
3. The site is clean and tidy, and no debris is piled up.
3. The lighting, water source, power supply, etc. required for the installation of the installation have been prepared.
4. The lifting and transportation equipment used in the device has operating conditions.
5. Storage facilities for spare parts, accessories and tools are available.
6. All kinds of large equipment around the installation equipment and the large pipes on the pipe gallery above have been hoisted.
7. Equipped with necessary fire-fighting equipment and dust removal equipment.